Completed
#0775 sort completed tasks by completed date
I'm wondering if there's a way, or there will be a way, to use the filter and list completed tasks by the completed date instead of the creation date.
Since I'm guessing that's not possible, is there a way to do it though a report? I haven't found an example to help me. Is there a list of functions and what they do? That would probably help with doing other reports.
Submitted by:
<eric>
22-Sep 2008
1 month and 4 weeks and 1 day old
1 month and 4 weeks and 1 day old
There is a way. By default the issuetracker sorts by creation date but you can change this to be by modification date. The modification date of an issue is always the same as the creation date of the latest followup within it.
The drawback is that changing this changes the whole issuetracker you're using.
23-Sep 2008